Commissioning Fire Extinguishing Devices (Standard); Commissioning The Fire Alarm Control Panel (Standard) - Huawei FusionDC1000A Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
Procedure
Step 1 Open the magnetic lock of the main entrance door by swiping an access card.
Step 2 Rotate the door handle clockwise and pull the main entrance door.
Step 3 Enter the pre-fab. module and close the main entrance door.
Step 4 For the main entrance door, press the exit button and push the door lever to open
the door. For the emergency door, push the door lever to open the door.
Step 5 Check the main entrance door event or emergency door alarm event in the
management system.
Step 6 Insert the key delivered with the emergency door release button into the test hole
to control the emergency door release button, and rotate the door handle
clockwise. If the door of the pre-fab. module can be opened, the emergency door
release button functions properly.
----End
4.5 Commissioning Fire Extinguishing Devices
(Standard)

4.5.1 Commissioning the Fire Alarm Control Panel (Standard)

Prerequisites
Initial configuration parameters have been set for the fire alarm control panel
before delivery and do not need to be set onsite.
Preparations
Tools: none
Documents required: power supply and distribution system diagram, documents
delivered with the fire alarm control panel, fire extinguishing system conceptual
diagram (standard), fire extinguishing device layout diagram (standard)
Skill requirement: fire engineer
Issue 02 (2022-12-15)
NO TE
If you do not open the main entrance door within 6s after swiping the card, the magnetic
lock will lock the door again.
NO TE
Normal response: The main entrance module door can be opened, and the management
system logs the door opening event.
NO TE
Normal response: The pre-fab. module door can be opened, and the management system
logs the door opening event.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Commissioning Core Devices
45

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents