Table Of Contents - Huawei FusionDC1000A Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
Contents
Contents
About This Document................................................................................................................ ii
1 Safety Information.................................................................................................................. 1
1.1 Personal Safety.........................................................................................................................................................................2
1.2 Electrical Safety........................................................................................................................................................................ 4
1.3 Environmental Requirements.............................................................................................................................................. 8
1.4 Mechanical Safety.................................................................................................................................................................10
1.5 Equipment Safety.................................................................................................................................................................. 15
1.5.1 UPS Safety............................................................................................................................................................................ 16
1.5.2 Cooling System Safety..................................................................................................................................................... 17
1.5.3 Battery Safety..................................................................................................................................................................... 17
2 Commissioning Guide Usage.............................................................................................. 25
3 Preparations for Power-On Commissioning....................................................................26
3.1 Tools.......................................................................................................................................................................................... 26
3.2 Reference Documentation................................................................................................................................................. 28
3.3 Commissioning Personnel Skill Requirements............................................................................................................ 28
3.4 Check Before Power-On...................................................................................................................................................... 29
4 Commissioning Core Devices.............................................................................................. 34
4.1 Commissioning the Integrated UPS................................................................................................................................ 34
4.1.1 (Optional) Commissioning the ATS............................................................................................................................ 34
4.1.2 Powering On and Starting the UPS.............................................................................................................................35
4.1.2.1 Power-On.......................................................................................................................................................................... 35
4.1.2.2 Starting the Inverter......................................................................................................................................................36
4.1.2.3 Powering On Loads....................................................................................................................................................... 36
4.2 Commissioning the SmartLi.............................................................................................................................................. 37
4.2.1 Connecting the Battery Supply..................................................................................................................................... 37
4.2.2 Powering Off Batteries.................................................................................................................................................... 41
4.2.3 Performing EPO..................................................................................................................................................................42
4.2.4 Clearing the EPO State.................................................................................................................................................... 42
4.3 Commissioning Smart Cooling Products.......................................................................................................................43
4.4 Commissioning Monitoring Devices............................................................................................................................... 44
4.4.1 Commissioning the Access Control System.............................................................................................................. 44
4.5 Commissioning Fire Extinguishing Devices (Standard)........................................................................................... 45
Issue 02 (2022-12-15)
Copyright © Huawei Digital Power Technologies Co., Ltd.
iv

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents