Section 11
Testing functionality by secondary injection
ANSI07000188 V1 EN-US
Figure 35:
11.17

Basic IED functions

11.17.1

Parameter setting group handling SETGRPS

Prepare the IED for verification of settings as outlined in section
11.17.1.1

Verifying the settings

1.
Check the configuration of binary inputs that control the selection of the active setting group.
2.
Browse to the ActiveGroup menu to achieve information about the active setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test /Function status/
Setting groups /ActiveGroup
The ActiveGroup menu is located on the PCM600 under Main menu/Test/Function status/
Setting groups /ActiveGroup
3.
Connect the appropriate dc voltage to the corresponding binary input of the IED and observe the
information presented on the local HMI.
The displayed information must always correspond to the activated input.
4.
Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting groups are
described in the corresponding PCM600 documents and instructions for the operators within the
SCS are included in the SCS documentation.
214
Test of RTC with I/O
© 2017 - 2021 Hitachi Power Grids. All rights reserved
1MRK 511 403-UUS Rev. K
"Preparing for test"
in this chapter.
Bay control REC670
Commissioning manual
SEMOD52026-1 v1
M11369-2 v4
M11369-4 v5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion rec670

Table of Contents