Completing The Test; Apparatus Control Apc - ABB Relion 670 Series Commissioning Manual

Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

1MRK 511 403-UUS Rev. K
The output READY shall be low, and PREP3P shall be high.
2.
Apply a single phase fault and thereby a RI signal.
3.
Check that a definitive three phase trip and no auto reclosing takes place.
Testing auto reclosing in a multi-breaker arrangement
The usual arrangement is to have an auto recloser per circuit-breaker. They can be in different circuit
breaker related IEDs or in a common IED.
A master auto recloser is set with Priority = High.
A slave auto recloser is set with Priority = Low.
The two auto reclosers can be checked individually by carefully applying RI , WAIT, and INHIBIT signals.
It is also possible to verify the two functions together by using circuit breaker simulating equipment for
two circuit breaker circuits. There should be interconnections from the master to the slave function,
WFMASTER- WAIT, and UNSUCCL - INHIBIT, as shown in the illustration referred to above.
Restoring equipment
After the tests, restore the equipment to normal or desired state. Check the following items in particular:
1.
Check the operation counters.
Reset the counters to zero, if that is the user's preference. The counter reset function is found on
the local HMI under Main menu /Reset /Reset counters /AutoRecloser79,5(0–>1) /
SMBRREC(79,5(0–>1)):x
2.
Restore settings that may have been modified for the tests back to normal.
3.
Disconnect the test switch, circuit breaker simulating arrangement and test circuits.
Reconnect any links or connection terminals, which may have been opened for the tests.
4.
Reset indications, alarms and disturbance recordings.
Clearing of the disturbance report can be done via the Disturbance Handling in PCM600 or the
local HMI.
11.10.2.5

Completing the test

Continue to test another function or end the test by changing the TESTMODE setting to Disabled.
Restore connections and settings to the original values, if changed for testing purposes.
11.10.3

Apparatus control APC

The apparatus control function consists of four types of function blocks, which are connected in a
delivery-specific way between bays and to the station level. For that reason, test the total function in a
system, that is, either in a complete delivery system as an acceptance test (FAT/SAT) or as parts of that
system.
Bay control REC670
Commissioning manual
See the application manual for an illustration of typical interconnections.
If a block/unblock command is sent from remote to function, while the IED is shut down,
this command will not be recognized after the start up, thus the command that was sent
prior to the shut down is used. In such cases, where there is a mismatch, the user is
advised to make a complete cycle of block/unblock operations to align the statuses.
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Section 11
Testing functionality by secondary injection
M12400-185 v7
M12400-190 v6
M12400-218 v5
M13385-2 v8
177