3.4.7 Insulation Test

Set the multimeter to the megohm range, and measure the resistance between the
lower support and the U-bar support. If the resistance is greater than 5 megohms, the
circuit is an open circuit, and the installation thus ends. Otherwise, the lower support
is not insulated from the U -bar support. In this case, remove all the installation parts
and check whether the insulating covering is missing or damaged. Repeat the
installation of the lower support, and perform insulation test again.

3.4.8 Installing Cabinet

Place the upper support (being fixed already at the lower part of the cabinet upon
delivery) on the lower support, push in and fix the cabinet with bolts to complete the
installation, as shown in Figure 3-21.
Figure 3-21 Installation on the cement ground with insufficient bearing capacity