Installation Manual
Airbridge cBTS3612 CDMA Base Station
3.3.2 Cabinet Installation Process
The installation process on the anti-static floor is shown in Figure 3-10.
Start
Position the
cabinet
Position the
support
Fix the support
Install the
low rack
Insulation test
Test passed?
Install the cabinet
End
Figure 3-10 Installation process on anti-static floor
3.3.3 Locating Cabinet
I. Determine the cabinet location
The installation position of the cabinet should be determined based on the predefined
benchmark dimensions in project plane design. When doing this, try to avoid the
interference between the installation supports and the anti-static floor framework. Try
as much as possible to keep the intactness of the framework. If the interference is
unavoidable, remove the floor framework at the place where the interference occurs
during the installation. The first cabinet should be aligned with the floor edge.
N
Y
3-11
Hardware Installation
3 Cabinet Installation