6.1.2 Monitoring the Output Power of TRXs

This describes how to obtain the output power of the TRX, which indicates the running status
of the TRXs.
Procedure
Step 1 Connect the power meter to the ANT port on the RFU.
Step 2 In the navigation bar of the Site Maintenance Terminal System window, choose Site. In the
browse window, double-click RF Specification Test. The Please select RC to test dialog box
is displayed. Select the board to be tested, as shown in

Figure 6-1 Please select RC to test dialog box

Step 3 Click OK. The RF Specification Test dialog box is displayed, as shown in

Figure 6-2 RF Performance Test dialog box

Issue 02 (2009-04-20)
NOTE
The fault points are usually at the connection point between the jumper and the feeder or between the
jumper and the antenna.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 Optional Commissioning Tasks