XVIII. Inspection of equipment installation
An overall inspection of the equipment installation is carried out in this step,
particularly the inspection of cable connections and routing.
XIX. Check of the standing wave ratio of antenna feeder
This step is to check installation conditions of all antenna feeders through the test of
standing wave ratio and backward & forward power.
XX. Equipment power-on
Power on the equipment after confirming that there is no abnormal short-circuit in the
equipment. Observe the status of each board.
&
Note:
This chapter aims to introduce the BTS hardware installation flow. For the detailed installation process,
please make adjustments according to the actual configuration and environment and perform the
process referring to relevant processes of Huawei.
1 Overview of Installation Process
1-8
Hardware Installation