Airbridge cBTS3612 CDMA Base Station
tighten the nuts to 4 5N
completely.
A board should be plugged into its slot in order as shown in Figure 3-6.
(1) Lower support
(5) Big plain washer Ö12
(8) Exploded expansion bolt M12×80
Figure 3-6 Lower support installation

3.2.4 Leveling

Place a level bar in vertical direction on the top-plane of the lower support to check
the levelness of the lower support. When errors occur, adjust the levelness by adding
washers beneath the lower support as shown in Figure 3-6.

3.2.5 Insulation Test

Set the multi-meter at the resistance measurement position. Cont act the cabinet and
expansion bolts respectively with the two measuring probes of the multi-meter to
measure the resistance. If the circuit is disconnected, complete the installation.
Otherwise, it indicates that the cabinet is not insulated. In this case, check whether
any insulating covering or insulating washer is missing, or whether any insulating
covering is damaged. Repeat the installation of the lower support and perform the
insulation test again.
&
m so as to pull the expansion bolt until it expands
(2) Spring washer Ö12
(6) Washer
3-7 
3 Cabinet Installation
(3) Nut
(4) Insulating covering
(7) Insulating plate
Hardware Installation

Advertisement