Preparing U-Bar Supports - Huawei Airbridge cBTS3612 Installation Manual

Cdma base station
Hide thumbs Also See for Airbridge cBTS3612:
Table of Contents

Advertisement

Installation Manual
Airbridge cBTS3612 CDMA Base Station
Start
Prepare the
support U-bar
Position cabinet
Fix the support
U-bar
Install the
low rack
Insulation test
Test passed?
Install the cabinet
End
Figure 3-16 Installation process on the cement floor without sufficient bearing capacity

3.4.2 Preparing U-bar Supports

When the allowable even load of the ground is lower than 5.5kN/m
can not be installed against the wall, U-bar supports should be adopted to reduce the
load to the floor from the cabinet. The recommended material for the support is the
14b-3000 type of GB707-88 hot-rolled U-bar. The length is based on the actual
situation (The total length of the U-bar shown in the figure is 3000mm), Drill
installation holes for and fixing holes on the U-bar as shown in and Figure 3-18.
Remove all burrs and sharp edges; Finally paint the whole support with rustproof coat
and top-coat (The color of the coat should be the same with or similar to that of the
cabinet). Thus, the fabrication of U-bar support is completed.
N
Y
3-19 
Hardware Installation
3 Cabinet Installation
2
, and the cabinet

Advertisement

Table of Contents
loading

Table of Contents