Figure 4 Installation Diagram (Nonincendive, Division 2 Installation)
*1: Dust-tight conduit seal must be used when installed in Class II and Class III
environments.
*2: Installation should be in accordance with the National Electrical Code (ANSI/NFPA 70)
Sections 504 and 505.
*3: The configuration of Associated Nonincendive Field Wiring Apparatus must be FM
Approved.
*4: Associated Nonincendive Field Wiring Apparatus manufacturer's installation drawing
must be followed when installing this equipment.
*5: No revision to drawing without prior FM Approvals.
*6: Terminator and supply unit must be FM Approved.
*7: If use ordinary wirings, the general purpose equipment must have nonincendive field
wiring terminal approved by FM Approvals.
*8: The nonincendive field wiring circuit concept allows interconnection of nonincendive
field wiring apparatus with associated nonincendive field wiring apparatus, using any of
the wiring methods permitted for unclassified locations.
*9: Installation requirements;
Vmax Voc or Vt