6.1 Check Before Power-on Commissioning
Table 6-1 Hardware installation checklist
No.
1
2
3
4
5
Table 6-2 Electrical connection checklist
No.
1
2
3
4
5
Issue 03 (2018-01-25)
6
Check Item
The cabinet is clean, without redundant screws, copper
wires, or other debris.
The paint on the cabinet exterior is intact.
The cabinet door and lock work properly.
All labels are correct, clear, and complete.
The surrounding area of the cabinet contains no waste tape,
cable ties, paper, or packing materials.
Check Item
All cables are connected properly.
The ground cable is connected properly.
The excessive sections of ground cables and power cables
are cut off.
Phase cables are connected properly.
All circuit breakers are OFF.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Commissioning Guide
6 Commissioning Guide
Result
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No
Result
□Yes □No
□Yes □No
□Yes □No
□Yes □No
□Yes □No