Figure 4-58 Installing The Chs Large Batt Box Using The Chs2U Joint Bracket Kit; Figure 4-59 Removing Chs Large Batt Box Cover - NEC Univerge SV8100 System Hardware Manual

Hide thumbs Also See for Univerge SV8100:
Table of Contents

Advertisement

Issue 1.0
4 - 50
Figure 4-58
Installing the CHS LARGE BATT BOX using the CHS2U JOINT
BRACKET KIT
5.
Secure the CHS LARGE BATT BOX to the CHS BASE UNIT
using the CHS2U JOINT BRACKET KIT. Refer to
Installing the CHS LARGE BATT BOX using the CHS2U JOINT
BRACKET KIT on page
4.2.2
Battery Installation
1.
Loosen screw on front of CHS LARGE BATT BOX. Refer to
Figure 4-59 Removing CHS LARGE BATT BOX
2.
Swing cover outward and detach from CHS LARGE BATT
BOX.
4-50.

Figure 4-59 Removing CHS LARGE BATT BOX Cover

UNIVERGE SV8100/SV8300
Figure 4-58
Cover.
Installing the SV8100 Chassis

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Univerge sv8300

Table of Contents