Deployment Preparation; Planning - Huawei RP100 Commissioning Manual

Room presence
Hide thumbs Also See for RP100:
Table of Contents

Advertisement

HUAWEI RP100&RP200 Room Presence
Commissioning Guide

2.1 Planning

To deploy an RP system, complete the tasks listed in the flowchart shown in
ensure that all verification items are passed.
Figure 2-1 Deployment workflow
Table 2-1 Deployment steps
Task
Pre-unpacking check
Unpacking cartons
Labeling cables
Issue 01 (2015-02-12)
2

Deployment Preparation

Description
Check the equipment cases.
Unpack the cartons and
check the goods inside.
Sort and label the cables.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
2 Deployment Preparation
Figure 2-1
Remarks
If any exceptions exist,
contact the logistics
personnel.
If any exceptions exist,
contact the supply chain
personnel.
Sort and label the cables
according to the system
connection diagrams.
and
7