ACS550 User's Manual
Mechanical and Electrical Installation – FBA
Warning! Connections should be made only while the drive is disconnected
from the power source.
Overview
The FBA (fieldbus adapter) is a plug-in module that fits in the drive's expansion slot
2. The module is held in place with plastic retaining clips and two screws. The
screws also ground the shield for the module cable, and connect the module GND
signals to the drive control board.
On installation of the module, electrical connection to the drive is automatically
established through the 34-pin connector.

Mounting Procedure

Note! Install the input power and motor cables first.
1. Insert the module carefully into the drive expansion slot 2
until the retaining clips lock the module into position.
2. Fasten the two screws (included) to the stand-offs.
Note! Correct installation of the screws is essential for
fulfilling the EMC requirements and for proper operation of
the module.
3. Open the appropriate knockout in the conduit box and
install the cable clamp for the network cable.
4. Route the network cable through the cable clamp.
5. Connect the network cable to the module's network
connector.
6. Tighten the cable clamp.
7. Install the conduit box cover (1 screw).
8. For configuration information see the following:
• "Communication Set-up – FBA" below.
• "Activate Drive Control Functions – FBA" on page 184.
• The protocol specific documentation provided with the module.
183
1
2
7
X00301
5
6
3
4
X00302
Fieldbus Adapter

Hide quick links: