3-4 Setting Up Your Server

SELECTING SERVER SITE

Read the following precautions before selecting a suitable site for your server. The following
describes installation of the server and connections to the server.
The following figure illustrates a site suitable for installing the server.
Room that satisfies the
following conditions: *
<While operating>
Temperature: 10 to 35ºC
Humidity: 20 to 80%
Temperature gradient: ±10ºC/h
Atmosphere: 749 to 1040 hpa
<While halting>
Temperature: –10 to 55ºC
Humidity: 10 to 80%
Temperature gradient: ±15ºC/h
Atmosphere: 749 to 1040 hpa
100 to 120 Vac/200 to 240
Vac parallel bi-polar wall
power outlet with the
ground line.
Observe the following instructions to use the server safely. Failure to follow
these instructions may cause a fire, personal injury, or property damage. See
pages 1-3 to 1-9 for details.
Never attempt to lift the server only by two or less persons.
Do not install the server in any place other than specified.
Do not use the server in the place where corrosive gases exist.
Allow clearance of at least 150 mm in
front of and behind the server.
The server must be
fixed with stabilizers.
CAUTION
Clean and tidy room
* It is recommended that the server should be used in a room where
temperature is in the range between 15 to 25ºC.