4.2.2 Hoisting the ESS

Prerequisites
Hoisting Precautions
Table 4-1 Hoisting precautions
Stage
Before hoisting
Issue 08 (2022-11-15)
Before installing the equipment, check the ESS for damage, such as holes and
cracks, and check the equipment model. If the appearance is abnormal or the
equipment model is incorrect, contact your dealer.
Before hoisting, ensure that the crane and hoisting ropes meet the load-
bearing requirements.
The steel hoisting ropes are available.
An appropriate crane is selected based on standards of the crane company
and assessed by professionals onsite.
The doors of the ESS to be hoisted have been closed.
It is recommended that the ESS be hoisted outdoors when the weather is
clear and there is no wind.
When installing or removing the hoisting equipment, do not drag it on the
ESS to prevent scratches.
Precautions
Ensure that the crane can hoist a load greater than 50 t,
and the working radius is not less than 10 m. If the onsite
environment does not meet the required working
conditions, ask a professional to assess the conditions.