FusionModule1000A20 CT Solution
Maintenance Guide
Figure 5-61 Installing the battery protective panel
Step 7 Check whether the new VESDA batteries are working properly.
----End
Follow-up Procedure
Dispose of the removed VESDA power box batteries that are confirmed faulty.
Issue 01 (2019-02-25)
Turn on the standby power switch. If the power fault indicator is off, the batteries are working properly.
Copyright © Huawei Technologies Co., Ltd.
5 Parts Replacement
130