FusionModule1000A20 CT Solution
Maintenance Guide
Figure 5-31 UFLP panel
FE/GE0 and FE/GE1 at the INSIDE side;
connecting to monitoring devices outside the
pre-fab. module
Impact on the System
None
Preparations
Tool: Phillips screwdriver
Material: spare camera SPD module
Documents: peripheral monitoring device installation position diagram
Skill requirement: skilled technicians, common technicians, and pipeline technicians
Procedure
Step 1 Move the SLPU and UFLP to the specified installation position based on the peripheral
monitoring device installation position diagram.
Step 2 Remove screws securing the UFLP, and remove it from the SLPU slot.
Step 3 Remove screws securing the SLPU, and take the SLPU out of the cabinet.
Step 4 Install the secure a new SLPU in the original position.
Step 5 Insert the UFLP into the SLPU slot and secure it.
Step 6 Connect the network cable inside the pre-fab. module and the network cable of the peer
device outside the pre-fab. module to the corresponding ports on the UFLP.
----End
Follow-up Procedure
Dispose of the removed camera SPD module that is confirmed faulty.
Issue 01 (2019-02-25)
For the diagram, see the quick installation guide for the solution in use.
Copyright © Huawei Technologies Co., Ltd.
FE/GE0 and FE/GE1 at the OUTSIDE side;
connecting to the LAN switch inside the
pre-fab. module
5 Parts Replacement
103

Advertisement

Table of Contents
loading

Table of Contents