CHAPTER 4: 3 SERIES IEC61850 GOOSE
NOTE:
SR3 SERIES PROTECTIVE RELAY PLATFORM – COMMUNICATIONS GUIDE
3.6.
Open the directory of relay 228's GOOSE transmission until the status bit of
Virtual Input 1 (sVal) is displayed.
3.7.
Click and drag the bit labeled status value (sVal) into the first data item location
of the reception as shown. This action maps the status of Ind 1 (sVal) which is
Virtual input 1 into the first remote input of relay 254.
3.8.
If available, additional items from relay 228's TX1 transmission, or other GOOSE
messages loaded into Relay 254, could be mapped into the remaining 31
locations within relay 254's receive area. Select Save.
Once the CID file is modified, relay 254's power must be cycled to load the new CID file
settings for the GOOSE message into the on-line area to take effect.
4.
Testing.
To test the operation, proceed as follows:
USING THE IEC 61850 CONFIGURATOR
4-43