FIGURE 3-16
FIGURE 3-17
3 - 16
Commissioning of a Redundant System Setup
3. Highlight the Preferred secondary option using the navigation keys.
Next, press the OK key.
The Confirm Changes screen will be displayed.
CIU 888 display: Confirm Changes screen
4. Highlight the OK option using the display keys. Next, press the OK
key.
The secondary CIU 888 will be reset to the factory settings and will
reboot twice. Because the Entis Pro system(s) connected to the
CIU 888s is shutdown, redundancy switchover will be disabled
during reboot.
When commissioning of both the primary CIU 888 and secondary
CIU 888 has been completed, the role of each CIU 888 in the
redundant system setup is indicated in the Status Dashboard (see
FIGURE 3-17).
Status Dashboard of primary CIU 888 (left) and secondary CIU 888 (right)
Ensite Pro to CIU 888 Migration Manual
CIU 888
Part No.: 4417593_Rev09