Sf6 circuit- breaker
Table of Contents

Advertisement

Final coupling
Orientation
of column
Assembling
the centring pins
Depressurizing
the chambers
03- 2017
Installation
Chamber - Column Coupling
Rotate the column (1) so that the control mount (3) is the same side as the
two 'humps' on the breaking chamber casing (2).
Fit parts A, B & C to the centring pins (30) & (31) without locking them in place
so that they may be easily removed later on.
NOTE:
Pin (31) is longer than pin (30).
S Remove the cap (5) from the transport cover (4) and operate the valve (6)
to re- establish atmospheric pressure within the chambers.
REMINDER: transport pressure nitrogen: azote (N
(101.3 kPa).
S Refit the cap (5).
GE Information
3
1
2
C
B
A
6
4
30
31
) at 0.03 MPa at 20C
2
5
Continued on next page.
L31- 7142EN/02