The complementary installation procedure, devel-
oped below, imposes a lifting equipment with the fol-
lowing characteristics :
Support- frame assembly
Lifting and positionning the pole
Installing terminals with preparation of contact
surfaces
Installing the capacitors
Column - chambers coupling
Installing the operating device
Installation, continued
GE Information
3,000 daN)
(minimum)
H + 2 m
+
H
L31- 140EN/02
L31- 200EN/06
L31- 508EN/03
L31- 603EN/02
L31- 7143EN/01
L31- 7902EN/01
D2021EN/01