LUNA2000-100KTL-M1 Smart Power Control System
User Manual
6.2 Powering On the Smart PCS
Precautions
● Wear insulated gloves and use insulated tools to prevent electric shocks or
● Before turning on the AC switch between the Smart PCS and the power grid,
● Before the equipment is put into operation for the first time, ensure that the
● If the Smart PCS has not been used for six months or longer after being
Procedure
Step 1 Turn on the AC switch between the AC side of the Smart PCS and the power grid.
Step 2 Turn on the DC switches between the DC side of the Smart PCS and the ESS.
Step 3 Deliver a startup command on the SUN2000 app, SmartLogger, or the
management system, and wait for the system soft start.
Step 4 Observe the LED indicators to check the running status of the Smart PCS.
----End
6.3 Downloading the App
Functions
The SUN2000 app (also referred to as the app) is a convenient local maintenance
platform that connects to the Smart PCS through the WLAN and allows users to
query alarms, configure parameters, and perform routine maintenance.
Issue 02 (2023-01-10)
D ANGER
short circuits.
NO TICE
check whether the AC voltage is within the required range using a multimeter.
(See the local power grid standard.)
parameters are set correctly by professional personnel. Incorrect parameter
settings may result in noncompliance with local grid connection requirements
and affect the normal operations of the equipment.
installed, it must be checked and tested by professionals before operation.
NO TE
Before sending a startup command to the Smart PCS, ensure that the DC voltage is within
the normal range.
Copyright © Huawei Technologies Co., Ltd.
6 Power-On Commissioning
51