Figure 3-12 Installing connecting kits
----End
Installing the Cabinet on Channel Steel
Step 1 Determine the cabinet installation positions on the channel steel based on holes in the
marking-off template for channel steel installation.
Step 2 Drill cabinet mounting holes in channel steel by using a hammer drill.
Step 3 Use a pallet truck to move the cabinet to the installation position.
Step 4 Use common M12x45 bolts to secure the cabinets into the mounting holes in the channel steel
and tighten the bolts.
Step 5 Install anchor baffle plates, as shown in
Step 6 (Optional) When multiple lithium battery cabinets are combined, install connecting kits on the
top of adjacent cabinets, as shown in
----End

3.5.2 Connecting a PE Cable

Procedure
Step 1 Check that the BCU power switch is OFF, and remove the cover from the PDU.
Issue 02 (2020-03-17)
Channel steel and expansion bolts for securing the channel steel should be purchased by
the customer. The recommended channel steel width is 50 mm or more.
Ensure that the spacing between external sides of a channel steel is 800 mm. Secure
channel steel to the ground by using expansion bolts.
Cabinet mounting holes must be aligned with channel steel mounting holes, and secure the
cabinet to channel steel with bolts.
Copyright © Huawei Technologies Co., Ltd.
Figure
3-11.
Figure
3-12.