4 Commissioning
4.2
Initial start–up
– – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – –
– – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – –
General
machine data
Channel–specific
machine data
Axis
machine data
Fig. 4-1
General sequence of initial startup
General sequence
of initial startup
4-20
PCU 50.3:
HMI Advanced/
ShopMill/
ShopTurn
Configure the PLC
Load the basic program
Configure the drives
Configure the NCK
machine
Load the PLC
user project
NCK
functions
Cycles
(1) The first step in the startup sequence is to configure the control system, i.e.
to set up communication between all involved components. PLC, drive, and
NCK are put into operation.
References:
/IDS/, Commissioning Manual CNC Part 1 (NCK, PLC,
Drive), SINUMERIK 840D sl,
(2) The second step is to initialize the various functions; this involves several
runs. The startup sequence for these functions is described in the following
sections.
SINUMERIK 840D sl Commissioning Manual CNC: ShopTurn – 11/2006 Edition
NCU:
HMI Embedded/
ShopMill/
ShopTurn
Display
machine data
GUDs,
macros
© Siemens AG 2006 All Rights Reserved
11/2006
1
2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents