Installation and commissioning flowchart

Identify the frame size of your drive: R0...R2.
Plan the installation: select the cables, etc.
Check the ambient conditions, ratings and required
cooling air flow.
Unpack and check the drive.
If the drive will be connected to an IT (ungrounded) or
corner grounded system, check that the internal EMC
filter is not connected.
Install the drive on a wall or in a cabinet.
Route the cables.
Check the insulation of the input cable and the motor
and the motor cable.
Connect the power cables.
Connect the control cables.
Check the installation.
Commission the drive.
About the manual
Task
See
Technical
data:
Ratings
on page
Planning electrical installation
Technical data
on page
113
Mechanical
installation:
Unpacking the drive
page
19
Hardware
description:
Type code
Electrical
installation:
Connecting the power
cables
on page
32
Mechanical installation
on page
Planning electrical
installation:
cables
on page
29
Electrical
installation:
Checking the insulation of
the assembly
on page
31
Electrical
installation:
Connecting the power
cables
on page
32
Electrical
installation:
Connecting the control
cables
on page
34
Installation checklist
on page
Start-up and control with I/O
113
on page
23
on
on page
17
19
Routing the
37
on page
39

Advertisement

Table of Contents
loading

This manual is also suitable for:

Acs350

Table of Contents