6.2.1.1.2 Installing DC Power Cables
Precautions
● It is recommended that switches be installed for battery cables. Customers
● Install battery cables in the following sequence: 1. Install cables at the battery
Procedure
1.
Issue 23 (2024-03-15)
NO TICE
need to purchase switches by themselves. For details about the battery circuit
breaker specifications, see
terminals on the UPS side. 2. Install cables at the battery terminals on the
battery side.
Install battery cables.
–
External battery strings