4.1 Preparing for Power-On

Step 1 Check that the AC/DC PSU and main control module are inserted properly and the
latches are locked.
Step 2 Check that fan switches QF3–5 are turned on and the unit is properly grounded.
Step 3 Check that the input voltage meets the requirement.
Step 4 Check that the power cables are connected properly.
Step 5 Check that the water detection module is installed.
Step 6 If teamwork networking is required, check that the teamwork cables are correctly
connected.
Step 7 Check that the cable connections and DIP switch settings of the T/H sensors are
correct.
Step 8 Turn on the active power switch QF1 and standby power switch QF2.
----End

4.2 Power-On

Procedure
Step 1 Turn on the general switch.
Step 2 After the initial power-on, the Quick Settings screen is displayed. Log in as user
admin, as shown in
Issue 02 (2022-03-30)
4

Power-On Commissioning

Figure
4-1.
Copyright © Huawei Technologies Co., Ltd.
4 Power-On Commissioning
66

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol8000-c190d40edNetcol8000-c190d40ec

Table of Contents