ABB GOE 2600 Installation And Commissioning Manual page 44

Transformer bushing
Table of Contents

Advertisement

2.
Install the winding cables to the fixed bottom
contact.
3.
Install the washers and nuts. Tighten the nuts in a
crosswise sequence.
4.
Remove the bolts (6), the washers (7) and the
lifting tool (1).
End of instruction
44
CAUTION!
Make sure that there is no tension in
the winding cables. Tension in the
winding cables will cause damage to
the cables.
Torque
Please refer to the transformer
documentation.