ABB ACS580MV Commissioning Manual page 69

200kw to 6300 kw,3.3kv to 11 kv
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

Drive insulation test is not mandatory.
Setting parameters and checking control signals
Switch on the control and auxiliary power supply accordingly. Return to Drive
composer, select Refresh in menu View, get into the online mode.
Note: Refresh and check the service access level once restarting the connection, enter
again the service level passcode if needed.
Check the SW or firmware version.
Note: ACS-AP-W/S version should be checked also (folder \05_ControlPanel FW)
Set the license received from the MV Drives Supportline. The Par. 96.70 license state
should be Time unlimited.
NOTICE Below information should be provided to MV Drives Supportline for license
inquiry:
series number of the drive
series number of the BCON board
Note: The position of BCON series number is shown hereunder.
Standard Commissioning Process 69