Mechanical installation of converter
Converter is securely fixed to the floor.
INU cabinet and TRU cabinet have finished combination.
Converter doors must open and close easily.
The floor that the unit is installed on is of non-flammable material, as smooth as
possible, and strong enough to support the weight of the unit. Check the floor flatness
with a spirit level. The maximum allowed deviation from the surface level is 5 mm in
every 3 meters. Level the installation site, if necessary, as the cabinet is not equipped
with adjustable feet.
Roof-mounted fan units are installed.
Installation and damaged components. When inspecting the converter, attention must
be paid to bad affixed, loosed or damaged components.
Electrical installation of converter
Foreign parts, dust and moisture should not be present in the converter cabinets.
Insulation or voltage test of cables, MCB, and motor have been done according to the
manufacture specifications. An official test report must be available.
Control cable section:
Types and cross sections of control cables are suitable for the signal type and signal
level. The shield of analog cable need grounding properly.
Control cables are connected. Customer interface is available in document.
MCB control cables are connected directly to the converter.
The wirings of remote control cabling are completed.
Cabling of options (transformer / motor protection, tachometer etc.) are
completed.
For MBU configuration, forbid customer to set common point for open status,
close status and ready status!
Power cable and grounding section:
Grounding cables of MCB, converter and motor are connected and tighten. The cross
section of the ground cable must be bigger than 150 mm².
Types and cross sections of power cables are selected according to the
Engineering Guideline
All cable screens and equipotential bonding conductor are connected. The cross
section of conductor cable should be bigger than 50 mm² for motor cable length less
than 300 m, and bigger than 95 mm² for motor cable length bigger than 300 m.
MCB and motor cables are not fastened at both ends (cables and converter must be
pass the insulation test before connection).
All cables between TRU and INU should be connected .For bolts types and torque
requirement, see below table:
(2UBB013672).