Standard Commissioning Process 65
Fill in all necessary information.
Note: Must fill in the full type code in Drive configuration, such as:
ACS580MV-066-A04A-J5-
010+AUX0000+AWL0000+HAS0000+ARC0000+ASC0010+COL0001+EPC0021+CCS00
00+CMC0000+CEO0000+CPR0004+CSC0001+CSV0003+DMT0001+SEO0000+CIT000
0+EXT0000+FAT0000+FAD0002+FWE0000+FAB0000+GDS0001+HWS0000+TRR0073
+LOD0011+LCH0000+PCE0041+MCE0041+MCC0000+RMC0001+EAT0000+EWT0000
+MOF0120+MST0000+MHP0000+TSM0000+OCH0000+OCA0000+PAK0000+CPF0002
+TRV0000+SHT0000+SPP0000+SPF0050+SMV0066+CEP0012+PCM0100+WMT0001
The full type code can be copied from the project information in MoR by search the series
number. If necessary contact MV Drives Supportline.