20 Standard Commissioning Process
Bolt size
M3
Copper
M4
Steel/ Stainless steel
Copper
M5
Steel/ Stainless steel
Copper
M6
Steel/ Stainless steel
Copper
M8
Steel/ Stainless steel
Copper
M10
Steel/ Stainless steel
Copper
M12
Steel/ Stainless steel
Copper
M16
Steel/ Stainless steel
Copper
M20
Steel/ Stainless steel
Copper
The connection to system ground has to be established in compliance with local
regulations.
Main circuit breaker (MCB)
The type of MCB is selected as per
(2UBB013672).
The MCB is ready to be tested with the converter.
The MCB protection relay settings are set and tested, and it can be modified by
requirement of commissioning engineer.
Safety devices (door locks etc.) are tested and in operation.
Local operation of MCB is disabled, and the connection to switch or button is
canceled.
The wiring of the control & signal cables connecting with the converter is finished.
The user manual and technical specification is available.
Withstand voltage test of the MCB have been done according to manufacture
specifications. The official test report must be available.
Bolt type
ACS580MV Engineering Guideline
Tightening torque (Nm)
0.8
2
1.2
3
2
5.5
3
10 (aluminum busbar)/ 15(copper busbar)
6
20 (aluminum busbar)/ 30(copper busbar)
10
30 (aluminum busbar)/ 40(copper busbar)
15.5
90 (aluminum busbar)/ 120(copper busbar)
30
120 (aluminum busbar)/ 160(copper busbar)
52