Preventive Maintenance

Contents of this chapter

This section contains the maintenance schedule with recommended maintenance
intervals and instructions of some special preventive maintenance items, which should be
performed by qualified personnel.
WARNING Obey the instruction in
Manual
(2UBB004520). If you ignore them, injury or death, or damage to the
equipment can occur.

Maintenance schedule

The recommended intervals for maintenance and component replacement are based on
the normal operating conditions of the drive. The drive should be checked at least every
two years by qualified personnel whose recommendations should be followed. Depending
on the actual condition of the drive, the maintenance work can be carried out before or
after the recommended interval.
Legend
Description
I
Inspection (visual inspection and maintenance action if required)
P
Performance of on-site work (commissioning, tests, measurements or other work)
R
Preventive replacement