FusionDC1000B Prefabricated Modular Data Center
Quick Guide (2021, Saudi, ITC)
Step 3 Install two bolts on the outdoor side wall to hang the device.
Figure 2-8 Pre-installing two bolts
Step 4 Hoist the 13.5 kW integrated air conditioner to the installation position using a
crane and mount it on the two bolts that have been installed.
Figure 2-9 Mounting
Step 5 Align the air intake and exhaust vents on the indoor side of the 13.5 kW
integrated air conditioner with the air intake and exhaust vent holes on the pre-
fab. module, and install all bolts.