7. Checking installation operations and performing
trial run
For air conditioning system designs before initial settings, consult your dealer.

7-1. Flow of initial settings

In general, the initial settings are largely divided into 4 steps as follows.
By making initial settings along these 4 steps, the cause classification in case of trouble is clarified in each step
and the initial settings can be advanced efficiently.
Make the initial settings according to the following procedures.
Step-1 Initial settings for the air conditioning system
Make the system setting of AE-200/AE-50/EW-50 and unit setting of the air conditioning system, and register
the required licenses. This is also a step to make initial settings other than for the apportioned electricity
billing function and BACnet
(Refer to the AE-200/AE-50/EW-50 Instruction Book (Initial Setting) for making the system setting of
AE-200/AE-50/EW-50 and the unit setting of the air conditioning system, and registering the licenses.)
Step-2 Trial run of the air conditioning system
Check to see that the air conditioning unit and controller, etc. have the correct system configuration or to see
that the air conditioning unit is operating normally. (Refer to AE-200/AE-50/EW-50 Installation Manual for the
method of trial run.)
When not using
an apportioned
electricity billing
function
Step-3 Initial settings for the BACnet
Using the BACnet
®
(For BACnet
related settings, refer to the AE-200/AE-50/EW-50 Instruction Book (BACnet
When not using
an apportioned
electricity billing
function
Step-4 Trial run of BACnet
Check that the operational status and alarms for air conditioning units are being displayed and reported
correctly in the BACnet
operation or settings from the BACnet
WT07919X04
®
functions.
Initial settings for apportioned electricity billing function
Make initial settings for the apportioned electricity billing function.
(Refer to the AE-200/AE-50/EW-50 Instruction Book (Apportioned
Electricity Billing Function) for initial settings procedures for apportioned
electricity billing function.)
®
related items
®
Setting Tool, make settings related to BACnet
Trial run of apportioned electricity billing function
Carry out a trial run of an apportioned electricity billing function.
(Refer to the AE-200/AE-50/EW-50 Instruction Book (Apportioned
Electricity Billing Function) and the AE-200/AE-50/EW-50 Instruction
Book (BACnet
trial run procedures.)
®
function
®
Trial Run Tool; that the air conditioning units are operating in accordance with
®
Trial Run Tool.
When using an apportioned
electricity billing function
®
of AE-200/AE-50/EW-50.
When using an apportioned
electricity billing function
®
Apportioned Electricity Billing Function Trial Run) for
These steps (excluding the BACnet
electricity billing function trial run for accumulator
objects and their trend log objects) can be reversed.
35
®
Setting Tool).)
®
apportioned

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ae-50eEw-50eAe-50aEw-50aAe-200e

Table of Contents