7.5
First commissioning of the PLC completed
First commissioning of the PLC completed
You have completed the first commissioning of the PLC.
The PLC and NCK are in the following state:
• LED RUN illuminates GREEN continuously.
• Status display shows a "6" with a flashing point.
Continue with the steps for commissioning the SINAMICS drives.
You can access the HMI as follows:
Figure 7-18
CNC Part 1 (NCK, PLC, drive)
Commissioning Manual, 11/2006, 6FC5397-2AP10-2BA0
⇒ PLC and NCK are in cyclic operation.
PLC commissioning complete
7.5 First commissioning of the PLC completed
PLC commissioning