First Commissioning Of The Plc Completed - Siemens SINUMERIK 804D sl Commissioning Manual

Cnc part 1 nck, plc, drive
Table of Contents

Advertisement

7.5

First commissioning of the PLC completed

First commissioning of the PLC completed
You have completed the first commissioning of the PLC.
The PLC and NCK are in the following state:
• LED RUN illuminates GREEN continuously.
• Status display shows a "6" with a flashing point.
Continue with the steps for commissioning the SINAMICS drives.
You can access the HMI as follows:
Figure 7-18
CNC Part 1 (NCK, PLC, drive)
Commissioning Manual, 11/2006, 6FC5397-2AP10-2BA0
⇒ PLC and NCK are in cyclic operation.
PLC commissioning complete
7.5 First commissioning of the PLC completed
PLC commissioning
61