Figure 5-10 Installing a SIM card and a micro SD card
Step 6 Install the ECC800-Pro main control module in the card slot.
Step 7 Tighten the screws on both sides of the ECC800-Pro main control module.
Step 8 Reconnect signal cables to the ECC800-Pro main control module panel based on
the recorded information.
----End

5.4.2 Replacing the Management System

5.4.2.1 Replacing a VCN510

Prerequisites
Context
Videos cannot be recorded during the replacement of the VCN510.
Do not operate with power on. Take appropriate insulation measures.
Procedure
Step 1 Turn off the power switch of the VCN510, disconnect the power supply of the
VCN510, remove the cables from the VCN510, label the cables, and record the
original connection positions of the cables.
Issue 01 (2020-12-25)
Recommended tool: Phillips screwdriver
A VCN510 needs to be replaced.
A spare VCN510 of the same model is available and functional.