Figure 7-13 Cutting a hole on the suspended ceiling
Step 5 Put the high-speed dome IPC and the embedded bracket in the middle of the hole on the
suspended ceiling, and lock the three retainers, as shown in Figure 7-14.
Figure 7-14 Fixing the bracket onto the suspended ceiling
Step 6 Mount the plastic decorative cover onto the main body of the IPC. Rotate the cover clockwise
to fix it onto the bracket, as shown in Figure 7-15.
Figure 7-15 Installing the plastic decorative cover
----End
Issue 03 (2013-02-28)
NOTE
Use a screwdriver to fasten the screws and the retainers will automatically turn outward and press tightly
against the ceiling. In this way, the bracket is fixed onto the ceiling.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd
7 Installing a Day & Night High Speed Do me IPC
Suspended ceiling
Hole with a diameter of 240mm
76

Advertisement

Table of Contents
loading

Table of Contents