Step 5 Use a drill bit with a diameter of 5.5 mm to drill four holes at the positions marked on the
positioning label. Each hole is 40 mm deep. Use a hammer or a hard object to drive four white
expansion particles into the drilled holes, as shown in Figure 5-22. Ensure that the expansion
particles are not exposed out of the wall.
Figure 5-22 Sticking the positioning label
Step 6 Route the multi-connector cable out of the side cabling gap on the bracket base or through the
30 mm cable outlet on the top. Take four black 30 mm self-tapping screws out of the
accessory kit of the bracket. Hold the bracket with one hand, and align the four holes on the
lower cover with the four expansion particles installed on the ceiling. Use the four black self-
tapping screws to fix the bracket onto the ceiling, as shown in Figure 5-23.
Issue 03 (2013-02-28)
NOTE
When an IPC is installed using a ceiling-mounted bracket, the side cabling mode is often used for
cable routing. In this case, you need to use the pincers to open the side cabling gap on the base of the
ceiling-mounted bracket.
If the top cabling mode is used, you need to drill a hole with a diameter of 30 mm on the wall.
White expansion particles
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd
5 Installing a Vandal-Proof Do me IPC
Positioning label