6.4.10

Zero point adjustment

The flowmeter system is optimized through a zero point adjustment.
Performing a zero point adjustment
Note
Preconditions
Before a zero point adjustment is initiated, the pipe must be flushed, filled and at an absolute
flowrate of zero preferably also at operating pressure and temperature.
1. Flush out the flowmeter until a homogenous flow is established and the tubes completely
filled.
Figure 6-12
2. Establish zero flow for example by closing the shut off-valves.
3. Wait 1 to 2 minutes, for the system to settle, and then perform zero adjustment as
described in the following steps.
FC430 with HART
Operating Instructions, 05/2015, A5E03361511-AF
Best practice zero point adjustment with a by-pass line and two shut-off devices
Commissioning
6.4 Commissioning with PDM
105