3 Design and Installation of the 810D
3.2 Installing the SINUMERIK 810D
CCU3
1
1
Fig. 3-3
Assembling the SINUMERIK 810D
Installation notes
When mounting the SINUMERIK 810D, please observe the following points:
1. Ventilation gap above and below approx. 100mm
2. The shields of the motor leads must be connected after the shield plate has
3. The equipotential bonding conductor must be connected at each motor
4. Additional mounting depth is needed to install the connectors.
5. Keep to the specified screw tightening torques.
6. Tighten all the DC link busbar screws.
3-44
Battery
been installed, see Subsection 2.1.4.
SINUMERIK 810D Manual Hardware Configuration (PHC) - - 11.02 Edition
CCU box
DC link
busbars
Safety earth terminal
E Siemens AG, 2002. All rights reserved
03.02
12.95

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinumerik 810deSinumerik 810d powerlineSinumerik 810de powerline

Table of Contents