Site-Planning Checklist
Table 2-2
Site-Planning Checklist (continued)
Task No.
Planning Activity
3
Power evaluation:
Input power type
•
Receptacle proximity to the equipment
•
Dedicated (separate) circuits for redundant
•
power supplies
UPS for power failures
•
4
Grounding evaluation:
Circuit breaker size
•
5
Cable and interface equipment evaluation:
•
Cable type
Connector type
•
Cable distance limitations
•
Interface equipment (transceivers)
•
6
EMI evaluation:
Distance limitations for signaling
•
Site wiring
•
RFI levels
•
Catalyst 4500 Series Switches Installation Guide
2-18
Chapter 2
Preparing for Installation
Verified by
Time
Date
78-14409-08