Honeywell Enraf VITO 762 Installation Manual page 11

Table of Contents

Advertisement

Installation:
Refer to figures 2 and 4.
Remove optional lower IP adapter (7), nuts (3 pc.), instrument label(s) (5) and
lock washers (2 pc.) from the adjusting pipe (1);
Screw the flange (2) with G ½ threaded hole on the adjusting pipe till the
marked position.
Note:
Take care not to damage the flying leads when shifting the flange over
the flying leads;
Use a suitable pipe sealant on the adjusting pipe for sealing threaded part
of the flange;
Hook-up anchor weight(s) (if applicable). Maximum weight: 9 kg (20 lb) for 365
probe and 23 kg (50 lb) for 76x probes;
Position the gasket on the tank nozzle;
Make sure the probe is properly bonded before inserting the probe into the tank. If needed
use an electric cable with alligator clamps to ground the probe to the tank nozzle before
Wait at least 30 minutes after the last tank movement.
Slowly feed the temperature probe into the tank; be careful not to damage the
corrugated stainless steel tube when lowering the probe into the tank by making
sure it does not rub over the tank nozzle;
Secure flange (2) on the roof/well nozzle and make ground connection across
the flanges;
Lock the VITO probe by means of lock washer (3) and lock nut (4);
Place the instrument label (5) and secure it by nut (6);
Go to section: 2.5 Installation 762 VITO Interface.
Caution: Static Electricity Danger
installation.
Installation guide 762 VITO interfaces & VITO probes
Mechanical installation
Page 11