Advertisement

Installation guide 762 VITO Interfaces
& VITO, MTT, LT, MRT and MPT probes
June 2014
Part no. 4416.648
Rev. 9
Honeywell Enraf
P.O. Box 812
2600 AV Delft
Netherlands
Tel.: +31 15 2701100
Fax: +31 15 2701111
E-mail:
hfs-tac-support@honeywell.com
H
Website:
www.honeywellenraf.com
Installation guide 762 VITO interfaces & VITO probes
Page 1

Advertisement

Table of Contents
loading

Summary of Contents for Honeywell Enraf VITO 762

  • Page 1 Installation guide 762 VITO Interfaces & VITO, MTT, LT, MRT and MPT probes June 2014 Part no. 4416.648 Rev. 9 Honeywell Enraf P.O. Box 812 2600 AV Delft Netherlands Tel.: +31 15 2701100 Fax: +31 15 2701111 E-mail: hfs-tac-support@honeywell.com Website: www.honeywellenraf.com...
  • Page 2: Table Of Contents

    Table of Contents Table of Contents Preface ......................3 Safety ......................4 Safety aspects of the VITO Interfaces & probes..........4 Personal safety ..................... 5 Safety conventions....................5 Mechanical installation ................6 Recommended tools ..................... 6 Mechanical installation of 764/767/361/MRT temperature probe ....... 6 2.2.1 Installation in a vertical thermowell ..............
  • Page 3: Preface

    Enraf B.V. accepts no responsibility for any errors that may appear in this installation guide. Additional information Please do not hesitate to contact Honeywell Enraf or its representative if you require additional information. Installation guide 762 VITO interfaces & VITO probes...
  • Page 4: Safety

    The 762 VITO Interface is an instrument with intrinsically safe output/input circuits. Modification to the instrument may only be carried out by trained personnel which is authorized by Honeywell Enraf. Failure to adhere to this will invalidate the approval certificate.
  • Page 5: Personal Safety

    Safety Warning Improper installation of cable glands, conduits or stopping plugs will invalidate the safety approval of the 762 VITO Interface. “For electrical data see certificate”. Personal safety The technician must have basic technical skills to be able to safely install the equipment. When a probe is installed in a hazardous area, the technician must work in accordance with the (local) requirements for electrical equipment in hazardous areas.
  • Page 6: Mechanical Installation

    Mechanical installation Mechanical installation The mechanical installation is divided into the following sub-chapters:  Installation of 764/767/361/MRT temperature probe (section 2.2)  Installation of 765 water probe, 766/768/365 Combi probe (section 2.3)  Installation of 762 VITO Interface (section 2.5) Caution The VITO Interface and probe may be installed in hazardous areas.
  • Page 7 Mechanical installation Notes: We do not recommend using liquid filled thermowells in tanks with heated products. Due to the heating at the lower end, the liquid may circulate in the well which results in a temperature mismatch. We do not recommend using liquid filled thermowells on floating roof tanks. Due to ambient temperature influence at the higher end, the liquid may circulate in the well which results in a temperature mismatch.
  • Page 8: Installation Directly In The Tank, Suspended From Roof Nozzle

    When anchor weights are attached, maximum static load is: 9 kg (20 lb) for 361 probe (when Honeywell Enraf anchor weight – p/n 0815524 – is used, only use 3 weights); 23 kg (50 lb) for 76x probes. Refer to figures 2 and 3.
  • Page 9: Mechanical Installation Of 765/766/768/365 Vito Water (And Temp.) Probe

    Caution When anchor weights are attached, maximum static load is: 9 kg (20 lb) for 365 probe (when Honeywell Enraf anchor weight – p/n 0815524 – is used, only use 3 weights); 23 kg (50 lb) for 76x probes. Note: The 765 VITO water probe, 766/768 VITO and 365 MPT water and temperature probe cannot be installed in a closed well.
  • Page 10 Mechanical installation Note: There should be at least 50 mm (2”) free space between the sensitive part of the water probe and the tank shell (or any other large metal part in the tank, i.e. stilling well). Figure 4 Installation methods for 765 VITO water probe, 766/768 VITO and 365 MPT water &...
  • Page 11 Mechanical installation Installation: Refer to figures 2 and 4.  Remove optional lower IP adapter (7), nuts (3 pc.), instrument label(s) (5) and lock washers (2 pc.) from the adjusting pipe (1);  Screw the flange (2) with G ½ threaded hole on the adjusting pipe till the marked position.
  • Page 12: Removing Vito Temperature Probe On Cryogenic Tank

    Mechanical installation Removing VITO temperature probe on cryogenic tank Warning Open the vent screw when removing the VITO temperature probe from a cryogenic tank. This must be done to prevent the hose of the VITO temperature probe to shrink in an uncontrolled matter, which can harm persons.
  • Page 13: Installation 762 Vito Interface

    Mechanical installation Installation 762 VITO Interface The VITO interface is typically installed directly on top of the VITO probe / MRT (refer to section 2.5.1) For installations where the VITO interface cannot be installed directly on the VITO probe / MRT (e.g.
  • Page 14: Version With Optional Ip Adapter

    Mechanical installation  When the electrical installation is carried out at a later stage, the cover of the VITO Interface enclosure can be closed after verifying there is no wire or cable in the gap between the shield and the enclosure. Make sure the cover threading is clean –...
  • Page 15 Mechanical installation  Unpack the VITO Interface (preferable on the tank);  Remove the cover from the VITO Interface enclosure;  Clean the inside thread of the upper IP adapter (3b) which is already attached to the VITO housing;  Apply a light, smooth layer of Agip TOP 2000 grease over the inside threads of the upper IP adapter (3b) on the VITO Interface housing and over the outside threads of the lower IP adapter (3a) on the probe;...
  • Page 16: Installation Of Vito Interface In Close Proximity Of Vito Probe / Mrt

    Mechanical installation 2.5.2 Installation of VITO Interface in close proximity of VITO probe / MRT In some cases there is not sufficient space to install the VITO interface on top o f the VITO probe / MRT. In these cases a (preferable flexible) metal conduit is advised, although also a set of matching coupling and unions can be considered.
  • Page 17: Electrical Installation

    Electrical installation Electrical installation The entire electrical installation shall be in accordance with the International Standard IEC EC 60079-14 (Selection and Installation). Warning Make sure that all power to the associated instrument is switched off before opening the cover of the 762 VITO Interface. Failure to do so may cause danger to persons or damage the equipment.
  • Page 18: Vito Interface Wiring To Tank Level Gauge

    Electrical installation VITO Interface wiring to tank level gauge The VITO-MTT/LT/MRT Interface connection to associated Honeywell Enraf instrument is by a single twisted pair cable. The single pair provides both intrinsically safe supply to the interface as well as data communication between the interface and the associated gauge.
  • Page 19: Supply / Data Communication Connection For 361 Vito Mpt Probe, 76X Vito Probes And Mrt

    Electrical installation The shielding must be connected to ground at both ends of the cable. 3.2.2 Supply / data communication connection for 361 VITO MPT probe, 76x VITO probes and MRT Refer to figure 9.  Remove the cover from the VITO Interface enclosure (if not already removed);...
  • Page 20 Electrical installation  Connect the other twisted pair of gauge wire the terminals on the lower left hand side of the front (temperature) converter block: pin 1: - pin 2: +;  Re-install the black plastic shield on the front converter block. Figure 10 CEPS Interface for 365 MPT temperature and water probe Note: The 365 MPT temperature and water probe with the associated CEPS Interface...
  • Page 21: Sensor Connections

    Electrical installation Sensor connections The electronic circuits of the 762 VITO Interfaces are protected against electrical static discharge during transport and storage by metal jumpers placed on the temperature probe connectors. A dummy resistor of 10 is placed between the red and brown wires (VITO- MTT &...
  • Page 22 Electrical installation  Connect: VITO probe wiring as indicated in figure 12 or figure 13; MRT as indicated in figure 14; 2 or 3 separate RTD’s as indicated in figure 15; 361 MPT probe as indicated in figure 16; 365 MPT probe as indicated in figure 12 (water probe connection at rear module) and figure 16 (multiple spot connection at front module).
  • Page 23 Electrical installation Caution For grounding reasons, first connect the brown wires towards the level gauge (VITO interface is powered by the level gauge). Figure 12 Sensor connections (764/765/766 probe) to 762 VITO-MTT Installation guide 762 VITO interfaces & VITO probes Page 23...
  • Page 24 Electrical installation Caution For grounding reasons, first connect the brown wires towards the level gauge (VITO interface is powered by the level gauge). Figure 13 Sensor connections (767/768 probe) to 762 VITO-LT Installation guide 762 VITO interfaces & VITO probes Page 24...
  • Page 25 Electrical installation Caution For grounding reasons, first connect the black wires towards the level gauge (VITO interface is powered by the level gauge). Figure 14 MRT probe connected to 762 VITO-MRT Note: Non used MRT-elements connections should be left open. Installation guide 762 VITO interfaces &...
  • Page 26 Electrical installation Caution With RTD’s, first connect one of the common wires of each RTD to GND-REF0 / GND-REF1 / GND-REF2. Figure 15 Three separated RTD’s connected to 762 VITO-MRT Note: Non used RTD’s elements connections should be left open. Installation guide 762 VITO interfaces &...
  • Page 27 Electrical installation Caution For grounding reasons, first connect the black wires towards the level gauge (VITO interface is powered by the level gauge). Figure 16 MPT Multiple Spot (Pt100) connected to 762 VITO-MRT Note: Non used MPT elements connections should be left open. Installation guide 762 VITO interfaces &...
  • Page 28: Appendix A Dimensional Drawing Vito 764 Temperature Probe

    Appendix Appendix A Dimensional drawing VITO 764 Temperature probe ….764D…. ….764C…. ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 28...
  • Page 29: Appendix B Dimensional Drawing Vito 765 Water Probe

    Appendix Appendix B Dimensional drawing VITO 765 Water probe ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 29...
  • Page 30: Appendix C Dimensional Drawing Vito 766 Combi Probe

    Appendix Appendix C Dimensional drawing VITO 766 Combi probe ….766D ….766C ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 30...
  • Page 31: Appendix D Dimensional Drawing Vito 767 Temperature Probe

    ____________________________________________________ Appendix D Dimensional drawing VITO 767 Temperature probe ….767D…. ….767C…. ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 31...
  • Page 32: Appendix E Dimensional Drawing Vito 768 Combi Probe

    Appendix E Dimensional drawing VITO 768 Combi probe ….768D…. ….768C…. ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 32...
  • Page 33: Appendix F Dimensional Drawing 361 Mpt Temperature Probe

    Appendix Appendix F Dimensional drawing 361 MPT temperature probe ….361…D ….361…C ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 33...
  • Page 34: Appendix G Dimensional Drawing 365 Combi Probe

    Appendix G Dimensional drawing 365 Combi probe ….762 I …/. ….762Z…/. Installation guide 762 VITO interfaces & VITO probes Page 34...
  • Page 35: Appendix H Related Documents

    Appendix Appendix H Related documents Installation guide 854 Advanced Technology Gauge Installation guide 854 XTG Level Gauge Installation guide 877 FDI Field Display & Interface Installation guide 973 SmartRadar LT Installation guide 971 SmartRadar LTi Installation guide 970 SmartRadar ATi Installation guide SmartRadar FlexLine Instruction manual VITO Service Manual SmartRadar FlexLine...
  • Page 36 P.O. Box 812 2600 AV, Delft Netherlands We at Honeywell Enraf are committed to excellence. Your Honeywell Enraf distributor: Information in this publication is subject to change without notice. ® Enraf is a registered trade mark. © Enraf B.V. Netherlands Installation guide 762 VITO interfaces &...

Table of Contents