Thermal upgrade kit

Advertisement

Table 4
Check
Installation Procedures
The following sections detail the installation procedures for the Cisco 6100 thermal upgrade kit. This
kit is required when using a Cisco 6100 chassis with dual-port DMT-2 or quad-port flexi ATU-C
modules in your system.
Remove Power
The system should not be powered while you install and connect the Cisco 6100 system
hardware components.
Remove power to the system with one of the following methods:
78-10158-01
Installation Checklist (continued)
Installation Procedure
Apply the power to the system.
23.
Verify that the fan tray is operational.
24.
25.
Reseat all of the modules.
Connect the network interface module to the network (if applicable).
26.
Attach the Cisco 6100 chassis ventilation cover.
27.
Attach the new power rating label.
28.
29.
Verify that the Cisco 6100 front door is closed.
Connect the ViewRunner system to the Cisco 6100 (if applicable).
30.
Close the rear door (if applicable).
31.
Run the connection test procedures.
32.
Remove the fuses from the fuse and alarm panel
Turn off the breakers in the fuse and alarm panel
Installing the Cisco 6100 Thermal Upgrade Kit
Cisco 6100 Thermal Upgrade Kit Installation Procedures