DLP-L22 Turning On and Verifying DC Office Power on the NCS 2006 Shelf

Procedure
Step 1
To power up the node, insert the fuse into the fuse position according to site practice. The fuse rating must
not exceed 20A.
Step 2
If the NCS 2006 does not power up, check the voltage at the power source using a voltmeter. The voltage
should be 100 to 240 VAC +/-10 percent.
Step 3
Return to your originating procedure (NTP).
DLP-L22 Turning On and Verifying DC Office Power on the NCS 2006 Shelf
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Caution
Do not apply power to the shelf until you complete all the installation steps.
Cisco NCS 2000 Series Hardware Installation Guide
218
Connecting Power and Ground
This task turns on the power and verifies correct
power and returns on the NCS 2006 shelf.
Voltmeter
NTP-L2 Mounting the Brackets in ANSI
Configuration , on page
NTP-L5 Opening and Removing the Standard
Door of the NCS 2006 Shelf , on page
• Connect the chassis to the office ground. For
detailed instructions on how to ground the
chassis, see the
Electrostatic Discharge and
Grounding Guide for Cisco NCS 2000 Series
DLP-L19 Connecting Office Power (DC) to the
NCS 2006 Shelf ( Only), on page 209
DLP-L20 Connecting Office Power (DC) to the
NCS 2006 Shelf (ETSI Only), on page 213
Required
Onsite
None
163.
252.
.