Siemens SICHARGE UC Installation And Commissioning Manual page 77

Hide thumbs Also See for SICHARGE UC:
Table of Contents

Advertisement

SICHARGE UC MastPanto
6.4 Commissioning
7
Tighten the screws of the anchor points
8
Fix the cables in the cable entry
Checking the connections
No.
1
Measure and write down the following values before the first power on:
Earth loop impedance:
Insulation resistance:
DC cabling from the Pantograph rails to the charging station:
2
After checking the SICHARGE UC MastPanto, mount the covers of the electronics boxes
Switch on MastPanto
No.
1
Switch on the following switch elements on the SICHARGE UC charging station for the low voltage
cable/AC of the SICHARGE UC MastPanto
Backup fuse
Residual current operated circuit breaker
2
Measure and write down the following values:
Voltage AC
Voltage DC
DC polarity on the DC contactors
DC polarity on the pantograph
3
Wait until the Linux-Controller (ACD board) of the SICHARGE UC MastPanto has fully started.
4
Check the SW and configuration of the ACD board.
5
Setup the Wifi-router with sinec pni tool.
6
Enter the IP address192.168.3.169 and subnet mask 255.255.255.0.
7
Configure and change password.
8
Setup the Y sensor
9
Setup frost monitor to W=4 °C
10
After checking the SICHARGE UC MastPanto, mount the covers of the electronics boxes
11
Close the maintenance door
Functional Tests
No.
1
Check the status LED in the Mast [if present] (Green available / Red charging)
2
Press the charge stop button on the charger. Ensure HMI indicates that charge stop is pressed and
the Pantograph is moving up in standby position and status LED turns off
3
Open the door of the charger while it is powered on. Ensure HMI indicates that the door is open
and status LED turns off
76
Checklist item
Checklist item
Checklist item
Installation and Commissioning Checklist for SICHARGE
UC Product Information, 03/2023, A5E52548271-AA
P
F
N/A
P
F
N/A
P
F
N/A