4.3 Connection
UC150 charging station
PE conductor
AC connection cable
Ethernet cable connection for external communication
Ethernet cable connection for internal communication between charging station and dispenser
AC AUX cable to charge point
DC cable to charge point
Global DC shutdown loop (only possible with GEN2 Dispenser)
Figure 4-2
Connection of four dispensers
Connecting the power supply cable
Connecting the PE conductor
No.
1
Remove the sheath of the power supply cable to approximately 8 cm in length
2
Select a wire end ferrule for the appropriate conductor cross-section
3
Strip the insulation from the end of the conductor so that the remaining insulation extends up to
the ferrule
4
Properly attach the wire end ferrule to the conductor end
5
Insert the wire end ferrule into the terminal strip of the ground connection
6
Check the connection of the PE conductor to the PE terminal
7
Document the characteristics of the cable used for the installation
Type of cable
Cable cross section
Cable length
32
Checklist item
Installation and Commissioning Checklist for SICHARGE UC
Product Information, 03/2023, A5E52548271-AA
P
F
N/A

Advertisement

Table of Contents
loading

Table of Contents